Apart from South African National Grid Access SEZ to provide preferential power supply for the pre-construction, the SEZ will also build its own power plant specifically for the projects within the SEZ, the main technical indicators of the Captive Power Plant in the SEZ are as follows:
No. |
Description |
UOM |
Indicator |
||
1st Phase |
2nd Phase |
3rd Phase |
|||
A |
Construction project planning |
Year |
2018-2021 |
2021-2024 |
2024-2027 |
B |
Installed capacity |
MW |
2*300 |
2*600 |
2*600 |
1 |
Annual power supply |
X108kWh/a |
33 |
66 |
66 |
2 |
Annual heat supply |
GJ/a |
14543939 |
29087878 |
29087878 |
3 |
Water consumption per million kilowatts |
m3/GWs |
0.0813 |
0.0813 |
0.0813 |
4 |
Coal burning index |
Kcal |
5000+ |
5000+ |
5000+ |
5 |
Annual coal consumption |
0000 t |
132 |
264 |
264 |
6 |
Annual water consumption |
0000 m3 |
3800 |
7600 |
7600 |
7 |
SO2 emission concentration |
Mg/Nm3 |
33.05 |
33.05 |
33.05 |
8 |
NOX emission concentration |
Mg/Nm3 |
52.5 |
52.5 |
52.5 |
9 |
Gas emission concentration |
Mg/Nm |
9.99 |
9.99 |
9.99 |
10 |
Ash content |
104t/a |
25.2 |
50.4 |
50.4 |
11 |
Desulphurized gypsum quantity |
104t/a |
5.42 |
10.84 |
10.84 |
12 |
Staffing |
Person |
232 |
464 |
464 |
13 |
Project site area |
0000 m2 |
300 |
500 |
500 |
C |
Construction period |
Year |
4 |
4 |
4 |